As an extension of our ongoing work and in the most important promising areas in the city of Al-Khobar on the New Corniche Road and the waterfront, the fourth phase of Trust Villas was launched, as it is close to the sea and to the most important commercial centers, Al-Jawhara Mall, and Saudi entertainment projects. The project was designed to take advantage of the multiple spaces and gardens, as well as (Sky Light). .

The project completion rate reached 85%.
Accordion Content
The percentage of work in the Al-Thiqa Villas Project, Phase Four, has reached 85%, as the project’s external facade work has been completed, and the project will be delivered at the beginning of the fourth quarter of 2023.
Date
08/15/2023
The project completion rate reached 65%.
Accordion Content
The percentage of work in the Al-Thiqa Villas Project, Phase Four, reached 65%, as the facade work is almost complete, the air conditioning and electrical work has been completed, and 25% of the project has been reserved.
Date
05/18/2023
Finishing and interior work has reached 50% and reservations have begun
Date
03/05/2023
The structural work has been completed
Date
02/15/2023
The completion rate of the construction structure reached 80% and internal work has begun
Date
01/01/2023
The project completion rate reached 15%.
Thank God, the show apartment was inaugurated in the Al-Thiqa Residential Complex and Sales Center project, in preparation for receiving customers and receiving reservations. At the same time, a Wafi license (off-plan sales) was issued, as the company was qualified to be one of the most important companies in the region and to facilitate the sales process for customers.
The project completion rate reached more than 15% of the foundations and structural structure.
Date
11/30/2022
The main contractor for the project has been hired
The structural work has been completed, the project features have appeared, and internal work has begun, establishing central air conditioning , plumbing, electricity, and the smart home system.
The design and plans phase has been completed, and this project follows the series of Al-Thiqa Villas projects in its fourth phase. This project is distinguished by the exploitation of multiple spaces and gardens, as well as (skylight).
Date
01/11/2022
The designs, plans and visual identity of the project have been completed
The project is being constructed according to the highest international specifications and tests are being carried out to ensure the best results are provided. The construction rate has reached 50% for the structural structure and finishing work has begun.
The project is being constructed according to the highest international specifications and tests are being carried out to ensure the best results are provided. The construction rate has reached 50% for the structural structure and finishing work has begun.
Date
10/25/2022
Land was acquired in the Bahr district, near the new seafront
The works agreement was signed with the main contractor, Knowledge and Planning, which is a subsidiary company, to start the works, receive the plans, and inspect the project site to carry out the initial work on the project.
Land was acquired in the Al-Bahr district, opposite the new waterfront in Al-Khobar, with an area of 1,200 square meters, to construct 4 villas with an exceptional design.